jxProject 0
JxProject
2.7.1.2 - Gantt
User Documentation
June 19, 2012
Gantt: If you are familiar with using other project
management software packages then jxProject should have a look and
feel that is familiar to you. The software is based on the
Gantt Chart which was developed by Henry Gantt (1861-1919) to be used
for scheduling multiple overlapping tasks over a time period.
jxProject allows you to build dependencies between tasks and it
rebalances the project plan to reflect those dependencies.
Dependencies are often/usually referred to as constraints.
Main components of the jxProject Gantt interface:
Figure 1: The Gantt Interface
The labels used in describing the basic components of the
jxProject interface in Figure 1 will be used consistently throughout
this document.
Elements of the Gantt Chart: While we have Figure 1
starring at us lets cover a few basics. The tree table and the
Gantt Chart are closely related and only serve as alternative visual
representations of the exact same data. Each row in the table
represents the data in the same row in the Gantt Chart to the right.
The data which fuels these interfaces is a collection of user defined
tasks. These user defined tasks have relationships between each
other which are also user defined. That’s really all
there is to this tool. Sounds simple enough eh? However,
because of the variety of relationships you can define between tasks,
project plans often become amazingly complex. But no matter how
complex the project plan gets, it is simply a group of tasks and the
relationships between them. Now a few definitions:
1. Task: This is the “atomic
element” of a project plan. It has a start date, duration
and an end date. These are represented on the chart as black
outlined rectangles with a fine grained blue and white checkerboard
fill color.
2. Summary Task: This is a
“roll-up” of tasks which are considered “children”
of these tasks. A summary task must have at least one child
task. A summary task and its child task have a hierarchical
relationship. These are represented on the chart as solid black
polygons which are largely rectangular.
3. Link: This defines a
direct relationship between exactly two tasks where either or both
tasks can be summary tasks. One task of the link is called a
predecessor task and the other link is called the successor task.
These are represented on the chart as solid black lines between the
two tasks with the arrow head pointing at the successor task.
Resource User links are brown lines with “crows feet” on
the ends, no arrow heads.
4. Arbitrary Constraint: This
is a date constraint which appears as green/orange arrows in the
chart. An arbitrary constraint will dictate that a task must start
after or finish after a specific date. The finish after constraints
are single headed green arrows where start after constraints are
double headed green arrows. There are also must start before and
finish before arbitrary constraints.
5. Predecessor Task: Acts as
the primary or driver task in resolving the relationship between
itself and its successor task.
6. Successor Task: Acts as
the subordinate task in the linked relationship between two tasks.
Elements of the Tree Table: A tree table is what you
get when you cross a traditional GUI table with a traditional GUI
tree. It’s a table with expandable collapsible nodes.
The furthest left column of the tree table is the “key”
field and it can never be scrolled out of view. Every other
column in the table can be scrolled and the order of the columns can
be changed by dragging the columns into different positions using the
column headers. Now a few definitions:
Key: Each task has a key value which is unique to all
other tasks. The key values are assigned by the software but
the user can renumber them right clicking on the header. You can
increase and decrease the table row height by pressing the (keyboard
shift key and the right mouse key on the row table header)
simultaneously and dragging it towards the bottom to increase the
row height and towards the top to decrease the row height.
Task Name: This is the name of the task or description
of the task.
Resources: These are the names of people assigned to
this task. If this field is blank then the “default
resource” is assigned to the task. The first resource in the
list is the “span resource”, so if a task is “span”
driven, then the span resource schedule is what is used to calculate
the start time and duration of the task.
Work:
This is the aggregated work hours of all resources assigned to the
task during the duration of the task. A triangle in the upper left
corner of this field indicates that work is the driving or constant
parameter in the task and that span and duration are derived from
the the work value. For work driven tasks: Duration = the absolute
amount of time the task must endure in order to satisfy the required
amount of work time from all assigned resources. Span = the
aggregated work hours of the span resource during the duration of
the task. The span resource is the first resource assigned to the
task and is the first resource name in the list of resources. The
work of summary tasks cannot be set by the user and is an aggregate
of all is child task work values. NOTE: The custom schedule and time
zone of each resource is used in these calculations. Also, these
values are adjusted to represent Full Time Equivalent (FTE) values.
Example: A work driven task would be one where the addition
of resources would result in the task taking less time to complete
as there are more people to do the work. If the task were, “digging
a ditch”, adding more resources to the task would shorten its
duration depending on the amount of work hours each resource was
available over the duration of the task.
Span: This is the aggregated work hours of the span
resource during the duration of the task. A triangle in the upper
left corner of this field indicates that span is the driving or
constant parameter in the task and that work and duration are
derived from the the span value. For span driven tasks: Duration =
the absolute amount of time the task must endure in order to satisfy
the required span work time. Work = the aggregated work hours of all
of the assigned resources during the duration of the task. The span
resource is the first resource assigned to the task and is the first
resource name in the list of resources. The span of summary tasks
cannot be set by the user and is an aggregate of all is child task
span values. NOTE: The custom schedule and time zone of each
resource is used in these calculations. Also, these values are
adjusted to represent Full Time Equivalent (FTE) values. Example:
A span driven task would be one where the addition of resources
would NOT result in the task taking less time to complete. If the
task were, “Have a meeting to review requirements”,
adding more resources to the meeting would not make the meeting any
shorter, but does increase the amount of work spent on the meeting.
Duration: This value is defined as finish date –
start date. A triangle in the upper left corner of this field
indicates that duration is the driving or constant parameter in the
task and that work and span are derived from the duration value. For
duration driven tasks: Work = the aggregated work hours of all of
the assigned resources during the duration of the task. Span = the
aggregated work hours of only the span resource during the duration
of the task. The span resource is the first resource assigned to the
task and is the first resource name in the list of resources. NOTE:
The custom schedule and time zone of each resource is used in these
calculations. FTE values are not utilized in the display or edit of
duration values. The durations of summary tasks cannot be set by the
user. Example: A duration driven task would be one where the
task takes an absolute amount of time regardless of resources. If
the task were, “Wait 36 hours for paint to dry”, a
duration driver is the way to go.
% Complete: Has a range of 0 to 100. It is used
to indicate the amount of the task that is complete. For
summary tasks the % complete is aggregated from its child tasks and
is weighted by the amount of work the child task represents.
Resources: These are the first names of people
assigned to this task. If the field is blank then the “default
resource” is invisibly assigned to the task.
Rank: This is used to determine which task gets first
priority to the Resources which are assigned to it. If two
tasks have the same Resource assigned to them, the task with the
lower Rank value will be scheduled first. The Rank of a task
is determined by its row position and its constraints. Tasks
that are towards the top of the table will tend to get the lower
Rank values. A successor task always has a higher Rank value
than its predecessor. The Rank value is generated by the
constraint solver but there are several tools available to the user
to alter the ranking of tasks See the documentation on
Resource Leveling for more information.
Start: This is the start date of the task. This
is an editable field but it is only used to add or change the start
after constraint (Arbitrary Constraint) of the task which will be
described later in the constraints section.
Finish: This is the finish date of the task.
This is an editable field but it is only used to add or change the
finish after constraint (Arbitrary Constraint) of the task
which will be described later in the constraints section.
Predecessors: This is a comma delimited field of task
keys which are predecessors of this task. This field can be
used to add, edit or delete predecessor task links.
Successors: This is a comma delimited field of task
keys which are successors of this task. This field can be used
to add, edit or delete successor task links.
Priority: A user set of priorities from Lowest to
Highest. The priority value does not affect the scheduling of the
task.
Notes: The notes associated with the task. Best
accessed through the task edit dialog.
Info: A non-editable field which indicates a problem
with the task such as an arbitrary constraint violation.
WBS: A non-editable field showing the work breakdown
number for the task; (ie. 2.1.4)
Driver: A non-editable field
indicating a numeric value for the type of scheduling driver for the
task, work/duration/span.
Early Start(ES): The
earliest date/time that a task can start given its constraints.
Dominant constraints are: Links: Start-to-Start and Finish-to-Start
and Arbitrary constraint: Must-Start-After.
Late Start(LS): The latest date/time that a task can
start without impacting the scheduling of successor tasks or the
project end. Dominant constraints are: Links: Start-to-Start and
Start-to-Finish and Arbitrary constraint: Must-Start-Before.
Early Finish(EF): The earliest date/time that the task
can finish given its constraints. Dominant constraints are: Links:
Start-to-Finish and Finish-to-Finish and Arbitrary constraint:
Must-Finish-After.
Late Finish(LF): The latest date/time that a task can
finish without impacting the scheduling of successor tasks or the
project end. Dominant constraints are: Links: Finish-to-Start and
Finish-to-Finish and Arbitrary constraint: Must-Finish-Before.
Start Float(SF): The amount of time remaining after
subtracting the Early Start Time from the Late Start Time. SF = LS –
ES. Float is sometimes referred to as slack.
Finish Float(FF): The amount of time remaining after
subtracting the Early Finish Time from the Late Finish Time. FF = LF
– EF. Float is sometimes referred to as slack.
Criticality: A calculated value based on the critical
task criteria set by the user. These values cannot be edited, they
range in value from Lowest to Highest. Critical tasks are displayed
differently on the charts than non critical tasks.
Constraint Elements: This is a listing of constraints
which affect the scheduling of tasks. The user cannot directly
set the start or finish dates of any task; this is done by the
constraint solver which is contained within jxProject. The user
must define constraints which act upon the task in order to alter the
scheduling of a task.
1. Hierarchical: This is the parent/child relationship
which exists between a summary task and one or more tasks. A
summary task starts at the same time of the earliest start date of
its child tasks and ends at the latest finish date of its child
tasks. A child task is constrained to be scheduled within the
constrained scheduling of its parent/summary task. A summary
task can contain millions of child tasks.
2. Links: These define a direct relationship between
exactly two tasks where either or both tasks can be summary tasks.
One task of the link is called a predecessor task and the other link
is called the successor task. A task may have up to 1 billion links.
There are four link types:
a. Finish to Start (FS) (default):
The finish date of the predecessor task pushes the start date of the
successor task.
b. Finish to Finish (FF): The
finish date of the predecessor task pushes the finish date of the
successor task.
c. Start to Finish (SF): The start
date of the predecessor task pushes the finish date of the successor
task.
d. Start to Start (SS): The start
date of the predecessor task pushes the start date of the successor
task.
e. Resource User (RU): The
successor task is constrained to have a rank value that is greater
than the predecessor task.
f. Pseudo Links (Ra+, Ra-): These
are not links, but tools to alter the ranking of tasks. They appear
here only for completeness and are discussed in detail in the
resource leveling documentation.
4. Rank: The rank of a task determines the priority in
which it is scheduled with respect to the resources assigned. The
task with the lowest rank value gets resources before any other task.
Rank is only relevant when resource leveling is enabled and it serves
as the tie breaker in scheduling tasks which share the same
resource(s). See the resource leveling documentation for more
details.
5. Arbitrary: This constraint is used when the scheduling
of a task is determined by constraints which are outside the control
of the project. An example would be that you have a set of
tasks in your project which depend on the arrival of a piece of
equipment. You would put in the arrival date of the equipment
as an arbitrary constraint preceding those tasks which depend on the
presence of that equipment. A task may have at most one of each
kind of arbitrary constraint. There are four types:
a. Start After: The task must
start after this constraint.
b. Finish After: The task must
finish after this constraint.
c. Start Before: The task must
start before this constraint. (Not enforced by constraint solver)
d. Finish Before: The task must
finish before this constraint. (Not enforced by constraint solver)
Note: The start/finish before constraints
are not enforced by the solver. An impossible example: Task A must
start on Monday and must finish one day later (Tuesday) and has a
duration of 10.0 days. It is impossible for the constraint solver to
resolve this set of constraints. The task will finish 10.0 days after
it starts and an “Error” will appear in the Info column
of the Gantt table in indicate that the finish before constraint is
being violated.
6. Resources: Tasks are constrained to begin only when at
least one of the assigned resources is available to work.
If no resource is assigned, the schedule of the “Default
Resource” is used to satisfy this constraint.
Title Bar:
The
title bar contains the jxProject logo/icon followed by the file name
which is currently open. Only one file can be open at a time.
Menu Bar:
The
menu bar consists of drop down menus which provide access to most of
the functionality in jxProject. Each of the menus is shown and
outlined below.
File Menu:
· New: Create a new file.
· Open…: Open an
existing file (*.jxp)
· Recent Projects…:
Open a dialog showing the last 50 project files opened/saved.
· Close: Close the file
that is currently open.
· Save: Save the
currently open file
· Save As…: Save
the currently open file with a new name.
· Import XML: Import a
jxProject file which is in XML format.
· Export XML: Export the
jxProject file in XML format.
· Print Preview…: This
takes you to the print preview screen and you can configure the
printer or print from there.
· HTML/images…: This
takes you to the image preview screen. From here you can view and
alter the size of the images produced when you save the html file.
The output is a simple html file utilizing the images of the table
and chart.
· 1: file:/c/...
There will be a listing of up
to 4 of the previously accessed files.
· Exit: Exit the
application
Edit Menu:
Cut/Copy/Paste:
Cut will copy the selected cells to the clipboard and set the values
to their minimum or default values. Copy will copy the cell values
to the system clipboard. Paste will paste values from the system
clipboard to the selected cells.
Fill Up: For multiple row selections, the top cell
value in a column will be copied down to all selected cells directly
below.
Fill Down: For multiple row selections, the bottom
cell value in a column will be copied up to all selected cells
directly above.
Delete Task(s): All fully selected rows/tasks will be
deleted.
Intent Task(s): Remove the selected tasks from their
current parent and insert them as children of the parent of the task
that is just above the top most selected task.
Outdent Task(s): Remove the selected tasks from their
current parent and insert them as children of their current
grandparent task.
Undo: Undo a previous edit such as add/delete task,
link, resource or an updating of the properties of a task, link ...
Redo: Redo an edit that was previously undone by an
undo.
Link Tasks: In the range of selected tasks (at least
2), working from top to bottom add a Task to Task link where the
upper task is the predecessor. The type of link created is
determined by what is selected in the Link Type selected in the pull
down menu off of the lower toolbar.
Un-Link Tasks: Remove any and all links which exist
between any of the selected tasks.
View Menu:
Insert Menu:
New
Tasks(s): This will insert a number of new tasks just above the
selected tasks. The number of tasks inserted will be the same
as the number selected. By default, new tasks are duration driven
and have a duration value equal to one unit of the current setting
of units in the Duration column of the Tree Table. So if the column
is in “Hours” then each new task would have an initial
duration of 1 hours.
Tools Menu:
License
Activation... : The Activation Dialog is accessed here. If
you have obtained a valid jxProject Serial Number, you can activate
the software to remove the scrolling advertising.
Update Advertisements... : Another dialog will
be presented asking you to confirm yes/no that you want to continue
with updating. If you select yes, the update progress dialog will be
placed into the sponsor window so you can monitor the progress of
the statistics upload and downloading of new advertisements. The
update process runs in a separate thread so you can continue your
work while the update progresses, you don't have to watch it. ;-) If
the update is successful it will turn green, if unsuccessful, it
will turn red. Either way it will then return to scrolling some
advertisements. If it has been less than two days since the last
advertising update, you will see a dialog that tells you the ads are
current and no updating will occur.
Network Settings... : This will bring up the Network
Settings Dialog just below the “Tools” text. This dialog
allows the user to set and test proxy settings. It is discussed
further later in this document.
Date Formats... : This will bring up the date format
dialog where you can add, edit or delete, the existing date formats.
See the chapter on Dates and time line formating for more detail.
Options...
: This will bring up the Options Dialog just below the “Tools”
text. The capabilities of the dialog are discussed later in
this document.
Help Menu:
Documentation:
A dialog directing you to go
to www.jxProject.com will be
shown.
Log Dialog …:
This will open the Log Dialog which will allow you to view log files
and their contents. You can also set the level of logging that is
done. Caution: Logging lots of data to the log file will slow down
the speed of the application, use the default logging levels for the
best performance and logging.
Sample Projects >:
There are three sample projects that the user can select and load in
order to get familiar with jxProject's capabilities. These files
can be edited and saved by the user, however, the sample projects
stored with the application are not altered.
About…: This will display the splash screen
showing the product name and version number.
Upper
Tool Bar: The tool bar acts provides quick access to
functionality which is accessible through the menu bar. Working
left to right the functionality is as follows:
New File; see Menu Bar > File >New
Open File; see Menu Bar > File > Open
Save File; see Menu Bar > File > Save
Print; see Menu Bar > File > Print
Display the resource assignment dialog. Used to
drag/drop resources onto tasks and to view resource schedules. (See
below)
Display the Options Dialog; This will open the options
dialog (See below)
Lower
Tool Bar: The lower tool bar provides the
following functionality: Working left to right the functionality is
as follows:
Switch to Gantt View; This
will switch the application to the Gantt View. If already in Gantt
view, it has no effect.
Switch to Schedule View; This
will switch the application to the Schedule View. If already in
Schedule view, it has no effect.
OP:
This will perform a single run of the resource optimizer. It will
attempt to identify a task which can be performed sooner than it is
currently scheduled without negatively impacting the schedule of any
other task. See the resource leveling documentation for more
details.
Outdent; see Menu Bar >
Edit > UnIndent Task(s)
Indent; see Menu Bar >
Edit > Indent Task(s)
Link; see Menu Bar >
Edit > Link Tasks
Un-Link; see Menu Bar > Edit >Un-ink Tasks
FS; This is a pull down menu to choose the kind of
link for creation during any task to task linking operation. The
letters used on this button will reflect the link type selected, so
it won't always say “FS” as shown in the picture
above. The possible link types are as follows:
Hard Links: FS, FF, SF, SS
Soft Link: RU – Resource User(RU) Link;
See the resource leveling documentation for more details.
Pseudo Links: Rank Adjustment (Positive – Ra+ or
Negative – Ra-) These are not really links, but tools
to alter the ranks of tasks relative to one another. See the
resource leveling documentation for more details.
Undo; see Menu Bar > Edit >Undo
Redo; see Menu Bar > Edit >Redo
Tree Table Interaction:
· Key:
Each task has a unique key that is assigned when each task is
created. You can renumber the tasks by “right clicking”
on the header which will bring up a single option popup-up menu to
renumber the tasks.
· Task Name: This is the
name or description of the task and you can type anything you like
into the field. The expand/collapse icons only appear on
summary tasks and you can click on those icons to expand or collapse
this task.
· Work: The default
display unit is hours. Clicking on the work value of a task you
will get a “spinner” editor with up and down arrow that
allows you to adjust in increments of 0.1. You can also type in
your own values without using the arrows if you like. You
cannot change the work of a summary task. NOTE: The work/span
times are Full Time Equivalent (FTE) adjusted. Example: Lets say an
FTE works 8.0 hours per day and the work in “Hours” is
24.0. If you change the work units to “Days” then the
value will be 3.0 as it takes 3 FTE days to produce 24 hours of work.
· Span: The default
display unit is hours. Clicking on the span value of a task you
will get a “spinner” editor with up and down arrow that
allows you to adjust in increments of 0.1. You can also type in
your own values without using the arrows if you like. You
cannot change the span of a summary task. NOTE: The work/span
times Full Time Equivalent (FTE) adjusted. Example: Lets say an FTE
works 8.0 hours per day and the span in “Hours” is 24.0.
If you change the span units to “Days” then the value
will be 3.0 as it takes 3 FTE days to produce 24 hours of work.
· Duration: This default
display unit is days. Clicking on the duration of a task you
will get a “spinner” editor with up and down arrow that
allows you to adjust in increments of 0.1. You can also type in
your own values without using the arrows if you like. You
cannot change the duration of a summary task. NOTE: The duration time
is NOT Full Time Equivalent (FTE) adjusted. Example: Lets say the
duration in “Hours” is 24.0. If you change the duration
units to “Days” then the value will be 1.0 as there are
24 hours in a day.
Gantt Table header context/pop up menu: The Column
Visibility option will bring up a dialog where you can see what
columns are available and can adjust the visibility, width and order
they appear in the table. The Date Format option is only available
for columns that require defined date formats such as start and
finish dates.
·Work/Span/Duration
Units: For the Work/Span/Duration fields you can change the units
for displaying and editing the value by using the mouse to right
click the Work, Span or Duration column header for the field and
selecting the units for display. The units for Work and Span
are FTE adjusted values. Duration units are NOT FTE adjusted.
· Start
Date: The date displayed is the start date of the task. If
you edit this field it will create a “start after”
arbitrary constraint for the task.
You
cannot type values into the date field, but you can select one of the
fields of the date with your mouse and the cursor will align to the
right of the chosen field. You can then increment or decrements
this part of the date with the spinner buttons or use your keyboards
up and down arrow keys. You can also change fields, left or
right using your keyboard arrow keys or picking with the mouse
cursor. You can change the format of the Start Date by right clicking
on the column header and selecting “Date Format...”. See
the chapter on Date Formating and TimeLines for more details.
· Finish
Date: The date displayed is the finish date of the task. If
you edit this field it will create a “finish after”
arbitrary constraint for the task.
You
cannot type values into the date field, but you can select one of the
fields of the date with your mouse and the cursor will align to the
right of the chosen field. You can then increment or decrements
this part of the date with the spinner buttons or use your keyboards
up and down arrow keys. You can also change fields, left or
right using your keyboard arrow keys or picking with the mouse
cursor. You can change the format of the Start Date by right clicking
on the column header and selecting “Date Format...”. See
the chapter on Date Formating and TimeLines for more details.
· Successors/Predecessors:
This is a validating comma delimited field of linked task keys.
Default link types which are Finish to Start do not have any
character designation but the other 4 links types(see constraints) do
have 2 character designators (SS, FF, SF, RU).
· Resources: To assign
resources to a task via this table you must bring up the resources
assignment dialog and drag one or more resources onto the task row to
which you want the resource(s) assigned. A resource in the
dialog is selected when the entire row is selected. To initiate the
drag you must press down the first mouse button on the “key”
cell of the selected resource(s) and begin dragging quickly. To
delete a resource from a task, double click the resource cell to
bring up the editor list of all the resources. Uncheck the
check box next to the resource name or set the % spinner to zero
which will also delete the resource from this task. The spinner
can be used to assign partial resources to tasks.
·
Table row header: The row header is the left most part of the
tree table which contains the “Key” field. You
change the table row height by pressing the keyboard shift key and
the right mouse key on the row header simultaneously and dragging
toward the bottom to expand the row height and toward the top to
compress the row height.
· Hot Keys/Accelerator Keys:
Shift+F10 will bring up the
table context menu; Shift+Space will select the entire row for any
selected cells; Cntrl+Space will select the entire column for any
selected cells; Alt+Shift+I will indent selected tasks; Alt+Shift+O
will indent selected tasks.
· Dragging and Dropping:
Using drag and drop it is possible to move or copy tasks. To initiate
a drag, select one or more tasks using the TreeTable row header to
select the entire row. Then press and drag the first mouse button on
the “key” field of the selected task(s). Do this quickly
so the drag gesture is recognized. Your cursor will change to reflect
the type of drag operation that has been initiated. The default drag
is a move, if you hold down the control key while initiating the
drag, the operation will be a copy. A copy cursor has a “+”
sign on it. When tasks are copied, links to tasks that are outside of
the group of tasks will be removed from the newly copied tasks.
· Tree Table
Context/PopupMenu: If you “right click” on a cell in
the Gantt Tree Table, or hot key Shift+F10 you will see the popup
menu above. Most of the selections are the same as the Edit menu.
However it also has options to expand or collapse the node. If you
select the associated “+” button, the operation will act
on all child/decedent tasks. For example, selecting the “+”
on the Expand Node item will expand the node and all nodes that are
children of that node, and any nodes that are children of those nodes
and so on.
Assigning Resources to tasks: To
assign resources to a task via this table you must bring up the
resources assignment dialog and drag one or more resources onto the
task row to which you want the resource(s) assigned. A resource
in the dialog is selected when the entire row is selected. To
initiate the drag you must press down the first mouse button on the
“key” cell of the selected resource(s) and begin dragging
quickly. If you want to assign one or more resources to
multiple tasks in a single step. Highlight only the resource cells in
the task table to which you want to assign resources, then drag
resources from the Resource Dialog and drop them onto the range of
selected resource cells. The resources will be assigned to all of the
highlighted tasks. If a task is already linked to one of the
resources, the existing relationship will be maintained and not
altered. You can also drop resources onto the tasks in the Gantt
chart. Also, you can drop tasks from the Gantt chart onto resources
in the dialog to make the associations.
Figure
2:
Assigning a resource to a task via Drag and Drop
The
spinner value associated with the resource is used to partially
assign resources to tasks. When you click the cell in the
table, click as far to the right as possible as the checkbox is very
sensitive and you can delete resources unintentionally. I don’t
like this interaction but it isn’t a show stopper so it makes
the TODO list. ;)
Figure
3:
Resource Table Cell Editor; for resource delete
Table Pan Scrolling/Auto scrolling: Pan scrolling the
tree table is activated by single clicking on the table with the
middle mouse button. The pan scroll will work for any component
inside a scroll pane and gives the user the ability to fly over the
component.
Gantt Chart Interaction: There is not a lot of
interactivity in the Gantt Chart but there are some things that you
can only do from the Gantt Chart so read closely.
Editing: Double
clicking on any item in the Gantt Chart will bring up the task edit
dialog. The item that was clicked will be selected/highlighted if
possible. You can edit or delete items associated with the task from
the dialog.
Creating/Modifying Arbitrary Constraints: You can
create these constraints by bringing up the context menu (right
click the Gantt chart) and selecting “Set Arbitrary” and
then the specific constraint that you want. The constraint will be
placed at the row and position where you clicked to bring up the
context menu. If there is a per-existing arbitrary constraint of the
type you you selected, it will be moved to the new location. You can
move arbitrary constraints once they are on the chart by selecting
them and then dragging them left or right. To drag a selected
constraint put the mouse over it, press down the first mouse button
and drag.
Creating/Modifying Links: You can link two tasks by
dragging from one row in the Gantt Chart to another. It is not
necessary to select the exact task itself from the row. If you
start to make a link but decide you do not wish to complete the
operation, release the mouse in the same row in which you started
the drag, or release it outside of the visible area of the chart.
The type of link created when you release the mouse is determined by
task link type setting in the toolbar pull down. You can modify the
lag of a link by selecting it and dragging it left/right. To drag a
selected link put the mouse over the point of the arrow head, press
down the first mouse button and drag left/right.
Modifying
Task Duration: You can modify the duration/work/span of any task
on the chart (not summary tasks). First select the task by clicking
on it. The place the mouse over the right most edge of the task,
press down the first mouse button and drag left/right. Note, the
“driver” of the task will affect how the task is
scheduled after the drag is complete. For duration driven tasks, the
task will end exactly where you release the mouse. However, for
work/span driven tasks, the task duration will adjust so that the
task stops during the work time of the resource(s) assigned to it.
Example: Joe works 8 – 5; M-F and is assigned to task A which
is a work driven task. You drag task A and release the mouse on
Saturday, when Joe is not working. The task duration will adjust to
finish at 8 the following Monday, or back to finish at 5 of the
previous Friday. Hint, use the “Flash schedule” option
to see where the “work time” is before dragging.
Pan
Scrolling/Auto scrolling: If you are dragging in the Gantt chart
you need to drag outside of the visible area of the chart in order
to make the chart scroll during the drag. This is inconsistent
with the behavior of the table which only scrolls when you are
inside the visible area. This will be fixed in a later
release. In the image above the user has activated pan scrolling by
single clicking on the chart with the middle mouse button. The pan
scroll will work for any component inside a scroll pane and gives
the user the ability to fly over the component.
·
Gantt chart header: The header defines the dates over
which the entire project extends. The upper scale is denoted in
weeks and the lower scale is in days. You can compress and
expand the time scale by pressing the keyboard shift key and the
right mouse key on the chart header simultaneously and dragging it to
the right to expand the scale and the left to compress the scale. As
you expand/compress the time line it will automatically change
formats to suit the level of scaling. There are at least 20 preset
formats for the header and they can be fully customized by the user
by the time line format dialog. Right click on the header and select
“TimeLine Format...”, and a dialog for customizing the
format will be displayed. See the chapter on Date Formating and
TimeLines for more details.
Gantt chart context menu: A
right click on the Gantt Chart or Shift+F10 will bring up this
context menu.
Edit... : This will bring up the
Task Edit Dialog for the task in the row.
Flash Schedule : This will show
the schedule time for the resources of the clicked task/row. The
schedule will display for about 5 seconds and then be cleared.
Set Arbitrary (Start-After,
Finish-After, Start-Before, Finish-Before): An arbitrary constraint
of the selected type will be placed at the point that the task/row
was clicked.
Chart Options... : This is brings
up the options dialog that can also be accessed from the Tools menu.
FTE-Work... : This brings up the
options dialog with the FTE tab visible.
Solver... : This brings up the
options dialog with the Solver tab visible.
Edit Task dialog: This
dialog is accessed by double clicking the “key” cell of
the Gantt Table or double clicking a row/task or item associated with
a task in the Gantt Chart.
The
above image shows the General tab of the task edit dialog. Most of
the items on this panel can also be edited through the table. For
summary tasks some of the fields are disabled such as percent
complete and driver/work/span/duration values, these values are
calculated from their child tasks.
The
above image shows the Dependencies tab of the task edit dialog.
Dependencies appear as “links” on the Gantt chart from
one task to another. Through this dialog dependencies can be added,
modified or deleted. In this image the user has typed a “?”
into the task name field which serves as a wild card search character
to find all tasks and display them in a dialog list for the user to
select one or more tasks as dependencies. The user can enter the
starting characters of any task and if there is just one match, that
task will be added, if more than one match, then they are shown in
the list. For example: if the user typed “buil” into the
task name field and hit return, the dialog would pop up with tasks 6
and 10 since they both start with “Build”. The search is
case insensitive. The user can also type the key # of any task in the
the ID column to add a dependency.
If the user double clicks on a link in the Gantt Chart, this
dialog will pop up and the selected link will be highlighted in the
table.
The
above image shows the Resources tab of the task edit dialog. Through
this dialog resources can be added, modified or deleted. In this
image the user has typed a “sfgh” into the Resource Name
field. As there were no resources with the name “sfgh” a
timeout dialog is shown to the user explaining that the search
returned no results and showing how the search was performed
[first=”” middle=”” last=””].
The resource name searches are
case insensitive and there are a variety of ways to search. Example:
“bob” would match “Bobby”
FFF just search
first name
LLL, just
search last name
LLL, FFF search last and first
name
LLL, FFF MMM search last and first
name and middle name
FFF LLL search first and last name
FFF LLL MMM search first and last
name and middle name
<SP>II just search resource
initials; Note: <SP> indicates white space entry
<SP>II<SP>I just
search resource initials start and ends with; Note: <SP>
indicates white space entry
? Return a dialog listing all
resources.
The user can also type the key # of any task in the the ID column
to add a resource.
The timeout dialog, shown in the above image, is an informational
dialog and has a countdown timer which starts as soon as it is
displayed. When the timer expires, reaches zero, the dialog goes
away. If you want to hold the dialog, click on the countdown number
to stop the countdown, double click on the number to dismiss the
dialog.
This
is the Options Dialog which allows the user to customize some
aspects of the behavior and appearance of application. There
are four “tabs” on the dialog and each will be discussed
below.
Gantt Tab: These are options to alter the appearance
of the Gantt chart.
“Display Resource Schedules”: If selected, the
schedules work time of resources assigned to the tasks will be
displayed in the rows containing the tasks. Note: this is a
computationally expensive operation and will cause a noticeable slow
down of the painting of the chart.
“Display Current Date Line (Verticle)”: If
selected, a purple vertical line will be drawn on the Gantt chart
which corresponds to the current date and time of the computer on
which the application is running.
“Display Non-work Day shading (Verticle)” : If
selected whole days where there is not work time scheduled for the
base schedule will be shaded gray. However, the header time line
lower scale must be in whole day units or the shading will not
appear.
“Display alternating row shading (Horizontal)”:
This will place a light shading on alternating rows of both the
table and the chart.
“Display Hard Links: [FS, FF, SF, SS]” If
selected, these hard link types will be displayed on the Gantt
Chart.
“Display Soft Links: [RU]” If selected, soft link
types will be displayed on the Gantt Chart.
Schedule Tab: These are options to alter the
appearance of the schedule chart.
“Render Tasks Assigned To Resources”: If
selected, the tasks assigned to a resource will be drawn over the
schedule of the resource on the chart.
“Display Current Date Line”: If selected, a
purple vertical line will be drawn on the Schedule chart which
corresponds to the current date and time of the computer on which
the application is running.
“Display Non-work Day shading (Verticle)” : If
selected whole days where there is not work time scheduled for the
base schedule will be shaded gray. However, the header time line
lower scale must be in whole day units or the shading will not
appear.
“Display alternating row shading (Horizontal)”:
This will place a light shading on alternating rows of both the
table and the chart.
“Render Summary Takes Assigned To Resources”: If
selected, summary tasks assigned to a resource will be drawn over
the schedule of the resource on the chart.
“Render Time Segments Location: If “CENTER”
is chosen, the time segments for each resource will be drawn in the
center of the row, tasks would be drawn over the time segments.
If “TOP” is selected, the time segments will be rendered
above the tasks which are being displayed.
Resource Assignment Tab: These are options to alter
the appearance of the schedule chart in the resource assignment
dialog.
“Render Tasks Assigned To Resources”: If
selected, the tasks assigned to a resource will be drawn over the
schedule of the resource on the chart.
“Render Summary Takes Assigned To Resources”: If
selected, summary tasks are drawn also.
“Render Time Segments Location: If “CENTER”
is chosen, the time segments for each resource will be drawn in the
center of the row, tasks would be drawn over the time segments.
If “TOP” is selected, the time segments will be rendered
above the tasks which are being displayed.
Solver Tab: These are options relating to how the
solver resolves constraints:
“Enable Resource Leveling”: If selected, tasks
will be scheduled so that resources assigned to them are never over
allocated.
“Super Solve”: This will force the solver to
completely recalculate the schedule. In most cases you won’t
see anything happen, however if you load a project file which was
not resource leveled, then push this button, you will likely see a
lot of changes as the leveling is enforced.
“Clean-up Solve”: This will go through all
pending model changes and solve them. There should never be
any pending model changes in the production version of the software
so you should never see anything happen when this is pressed. This
is mostly used for debugging during development.
FTE-Work Tab: These are options to define the work
hours of a full time resource:
Hours per Day: This is the number of hours an FTE will work
on a typical work day.
Days per Week: This is the number of full time work days an
FTE will work in a typical week.
Weeks per Month: This is the number of full time work weeks
an FTE will work in a typical month.
The values of “Hours per Week”, “Hours per
Month” and “Hours per year” are displayed and
updated on the panel to provide information to the user.
These FTE values are used in the Gantt Tree Table columns for
Work and Span. If a task takes 24 hours of work, and the FTE works 8
hours per day, then a work column displayed in days will have a
value of 3.0. 24.0/8.0 = 3.0.
Critical Tab: These are options which affect the
calculation, criteria and display of critical tasks. See the
document on “Critical Path Analysis”.
|